Bautagebuch vom 05. April 2018

[vc_row row_type="row" use_row_as_full_screen_section="no" type="full_width" text_align="left" css_animation=""][vc_column width="1/3"][vc_empty_space height="120px"][vc_column_text]Der Bagger ist mittlerweile angerollt und wartet auf seinen Einsatz.[/vc_column_text][/vc_column][vc_column width="2/3"][vc_single_image image="973" img_size="full" qode_css_animation=""][/vc_column][/vc_row][vc_row row_type="row" use_row_as_full_screen_section="no" type="full_width" text_align="left" css_animation=""][vc_column][vc_empty_space height="50px"][/vc_column][/vc_row][vc_row row_type="row" use_row_as_full_screen_section="no" type="full_width" text_align="left" css_animation=""][vc_column width="1/4"][vc_column_text][/vc_column_text][/vc_column][vc_column width="1/2"][vc_single_image image="974" img_size="full" qode_css_animation=""][/vc_column][vc_column width="1/4"][vc_column_text][/vc_column_text][/vc_column][/vc_row][vc_row row_type="row" use_row_as_full_screen_section="no" type="full_width" text_align="left" css_animation=""][vc_column][vc_empty_space height="50px"][/vc_column][/vc_row][vc_row row_type="row"...

Bautagebuch vom 28. Juni 2018

[vc_row row_type="row" use_row_as_full_screen_section="no" type="full_width" text_align="left" css_animation=""][vc_column width="1/4"][vc_empty_space height="80px"][vc_column_text]Nachdem die Abdichtung des Sockelbereiches fertiggestellt wurde, konnten im Hofbereich bereits die ersten Dämmplatten der Sockeldämmung (Perimeterdämmung) angebracht werden. [/vc_column_text][/vc_column][vc_column width="3/4"][vc_single_image image="1263" img_size="full" qode_css_animation=""][/vc_column][/vc_row][vc_row row_type="row" use_row_as_full_screen_section="no" type="full_width" text_align="left" css_animation=""][vc_column width="2/3"][vc_single_image image="1262" img_size="full" qode_css_animation=""][/vc_column][vc_column width="1/3"][vc_empty_space height="60px"][vc_column_text]Die Kanalrohre für die unterirdische...

Bautagebuch vom 13. September 2018

[vc_row row_type="row" use_row_as_full_screen_section="no" type="full_width" text_align="left" css_animation=""][vc_column width="1/4"][vc_empty_space height="80px"][vc_column_text]Die Arbeiten am rückwärtigen Gebäudeteil schreiten weiter voran. Die rückwärtigen Fenster im Erdgeschosses wurden bereits ausgebaut. [/vc_column_text][/vc_column][vc_column width="3/4"][vc_single_image image="1426" img_size="full" qode_css_animation=""][/vc_column][/vc_row][vc_row row_type="row" use_row_as_full_screen_section="no" type="full_width" text_align="left" css_animation=""][vc_column width="2/3"][vc_single_image image="1427" img_size="full" qode_css_animation=""][/vc_column][vc_column width="1/3"][vc_empty_space height="60px"][vc_column_text]Auch im zukünftigen Wohnbereich wurden die ehemaligen Fenster...

Bautagebuch vom 12. April 2018

[vc_row row_type="row" use_row_as_full_screen_section="no" type="full_width" text_align="left" css_animation=""][vc_column width="1/4"][vc_empty_space height="80px"][vc_column_text]Das Vordach oberhalb des Hauseinganges wurde mittlerweile abgetragen.[/vc_column_text][/vc_column][vc_column width="3/4"][vc_single_image image="1034" img_size="full" qode_css_animation=""][/vc_column][/vc_row][vc_row row_type="row" use_row_as_full_screen_section="no" type="full_width" text_align="left" css_animation=""][vc_column width="2/3"][vc_single_image image="1032" img_size="full" qode_css_animation=""][/vc_column][vc_column width="1/3"][vc_empty_space height="60px"][vc_column_text]Die vorhandenen Kellerschächte wurden allesamt vom Gebäudesockel entkoppelt, so dass die vorgesehene Sockeldämmung später ohne Unterbrechung...

Bautagebuch vom 19. April 2018

[vc_row row_type="row" use_row_as_full_screen_section="no" type="full_width" text_align="left" css_animation=""][vc_column width="1/4"][vc_empty_space height="50px"][vc_column_text]Eine weitere Zwischenwand in einem Büroraum im Obergeschoss wurde abgetragen.[/vc_column_text][/vc_column][vc_column width="3/4"][vc_single_image image="1041" img_size="full" qode_css_animation=""][/vc_column][/vc_row][vc_row row_type="row" use_row_as_full_screen_section="no" type="full_width" text_align="left" css_animation=""][vc_column width="2/3"][vc_single_image image="1040" img_size="full" qode_css_animation=""][/vc_column][vc_column width="1/3"][vc_empty_space height="50px"][vc_column_text]Für die zukünftige Nutzung nicht mehr benötigte Verbindungen zwischen den Räumen im zukünftigen Praxisbereich...

Bautagebuch vom 17. Mai 2018

[vc_row row_type="row" use_row_as_full_screen_section="no" type="full_width" text_align="left" css_animation=""][vc_column][vc_empty_space height="20px"][vc_column_text]Die massive Naturstein-Türeinfassung wurde mittlerweile entfernt und für den späteren Wiedereinbau gelagert. [/vc_column_text][vc_empty_space][vc_single_image image="1182" img_size="full" qode_css_animation=""][/vc_column][/vc_row][vc_row row_type="row" use_row_as_full_screen_section="no" type="full_width" text_align="left" css_animation=""][vc_column width="2/3"][vc_empty_space height="50px"][vc_single_image image="1180" img_size="full" qode_css_animation=""][/vc_column][vc_column width="1/3"][vc_empty_space height="100px"][vc_column_text]Ein Wiedereinbau der Elemente im Zuge der Erneuerung der Eingangstür ist vorgesehen.[/vc_column_text][/vc_column][/vc_row][vc_row row_type="row"...

Bautagebuch vom 21. Juni 2018

[vc_row row_type="row" use_row_as_full_screen_section="no" type="full_width" text_align="left" css_animation=""][vc_column][vc_column_text]Die Abdichtungsmaßnahmen im Sockelbereich können beginnen!  Die entsprechenden Bereiche wurden gründlich gereinigt, so dass in den ersten Teilbereichen bereits mit dem Auftrag der Dickbeschichtung bekonnen werden konnte...

Bautagebuch vom 12. Juli 2018

[vc_row row_type="row" use_row_as_full_screen_section="no" type="full_width" text_align="left" css_animation=""][vc_column][vc_single_image image="1378" img_size="full" qode_css_animation=""][vc_empty_space][/vc_column][/vc_row][vc_row row_type="row" use_row_as_full_screen_section="no" type="full_width" text_align="left" css_animation=""][vc_column][vc_column_text]Ein Großteil der Fenster im Erdgeschoss des Gebäudes wurde mittlerweile erneuert. Die neuen Fenster werden von außen auf die bestehende Mauerwerkswand gesetzt. Nach Einbau der Fassadendämmung werden sie schließlich optimal und wärmebrückenfrei innerhalb...

Bautagebuch vom 23. August 2018

[vc_row row_type="row" use_row_as_full_screen_section="no" type="full_width" text_align="left" css_animation=""][vc_column][vc_column_text]Die Arbeiten an der Fassade des Gebäudes schreiten weiter voran: nun wird auch im rückwärtigen Gebäudebereich der Sockelbereich abgedichtet und mit Wärmedämmung versehen.[/vc_column_text][vc_empty_space][/vc_column][/vc_row][vc_row row_type="row" use_row_as_full_screen_section="no" type="full_width" text_align="left" css_animation=""][vc_column][vc_single_image image="1406" img_size="full" qode_css_animation=""][vc_empty_space][/vc_column][/vc_row][vc_row row_type="row" use_row_as_full_screen_section="no" type="full_width" text_align="left" css_animation=""][vc_column width="2/3"][vc_single_image image="1408" img_size="full" qode_css_animation=""][/vc_column][vc_column...

Bautagebuch vom 06. September 2018

[vc_row row_type="row" use_row_as_full_screen_section="no" type="full_width" text_align="left" css_animation=""][vc_column][vc_column_text]Der ehemalige außenliegende Zugang zum Kellergeschoss wurde mittlerweile entfernt. Massive Bauteile wurden dabei vom Gebäude entkoppelt, der Sockelbereich wurde abgedichtet und mit Wärmedämmung versehen. Anschließend wurde der Kellerabgang verfüllt.[/vc_column_text][vc_empty_space][/vc_column][/vc_row][vc_row row_type="row" use_row_as_full_screen_section="no" type="full_width" text_align="left" css_animation=""][vc_column][vc_single_image image="1411" img_size="full" qode_css_animation=""][vc_empty_space][/vc_column][/vc_row][vc_row row_type="row" use_row_as_full_screen_section="no" type="full_width" text_align="left"...